CM Nitish to Inaugurate Munger Rail-Road Bridge

After years of delays, Muzaffarpur is finally set to get two much-awaited Road Over Bridges (ROBs) at Ramdayalu and Gobarsahi. The tenders have been finalized and awarded to reputed construction agencies from Bihar and Jharkhand. These new overbridges are expected to ease chronic traffic congestion in the city and on nearby highways.

Tender Finalized for Two Key ROBs

The Bihar State Bridge Construction Corporation Ltd. (BSBCCL) has awarded the construction contracts to:

  • Ramdayalu ROB – to Hardev Construction Pvt. Ltd., Jharkhand
  • Gobarsahi ROB – to Rachna Construction Ltd., Danapur, Bihar

This decision was finalized at the Patna office of BSBCCL. Both contractors will now undergo final documentation before construction begins.

What Happened to Sadpura ROB?

While tenders for Ramdayalu and Gobarsahi were approved, the Sadpura ROB tender was cancelled. Only two firms had bid:

  • One bid was rejected due to missing documentation
  • The remaining bid could not be approved as per departmental norms

The tender process for Sadpura will be reissued after headquarters approval, which is currently in progress.

Construction Timeline and Budget Details

Each ROB is expected to be completed within 30 months. Regular monitoring will be conducted to ensure timely progress.

ROB LocationConstruction CostAdministrative Approval
Ramdayalu₹1.87 billion₹2.48 billion
Gobarsahi₹1.22 billion₹1.67 billion
Total Cost₹3.09 billion

The extra budget will be used for maintenance and additional works over the next few years.

How These ROBs Will Change Muzaffarpur

The two new bridges are being built to eliminate traffic bottlenecks at key level crossings that are frequently closed due to passing trains.

Key Benefits:

  • Over 100 trains and goods carriers cross these gates daily, causing frequent gate closures every 10 to 15 minutes
  • Once operational, the new ROBs will replace level crossings, ensuring smooth traffic flow
  • Ramdayalu ROB will feature improved connectivity via Bhikhampur Mor, benefiting traffic from Hajipur and Bhagwanpur
  • Gobarsahi ROB will have a ramp leading to Dumri Road, connecting directly to NH-77 (Hajipur–Patna)

Both ROBs will be constructed in Y-shape designs for better traffic dispersal and structural efficiency.

Did You Know?

The delay at level crossings in Muzaffarpur causes an estimated daily loss of over 1,000 man-hours due to traffic standstills.

Key Takeaways

  • Ramdayalu and Gobarsahi ROB tenders finalized; construction begins end of May 2025
  • Sadpura ROB tender cancelled, will be reissued soon
  • ₹3.09 billion project to be completed in 30 months
  • City traffic and highway congestion expected to reduce significantly
  • Both ROBs to be built in Y-shape with modern traffic planning

FAQs

Which ROBs have been approved for construction?

Ramdayalu and Gobarsahi ROBs have received final tender approval.

Who will construct these ROBs?

Hardev Construction (Jharkhand) for Ramdayalu, and Rachna Construction (Bihar) for Gobarsahi.

Why was the Sadpura ROB tender cancelled?

Due to incomplete documentation and lack of competition; it will be reissued after HQ approval.

When will construction start?

Construction is expected to begin by the end of May 2025.

How long will the project take to complete?

Both projects are scheduled for completion in 30 months.